page 1
page 2
page 3
page 4
page 5
page 6
page 7
page 8
page 9
page 10
page 11
page 12
page 13
page 14
page 15
page 16
page 17
page 18
page 19
page 20
page 21
page 22
page 23
page 24
page 25
page 26
page 27
page 28
page 29
page 30
page 31
page 32
page 33
page 34
page 35
page 36
page 37
page 38
page 39
page 40
page 41
page 42
page 43
page 44
page 45
page 46
page 47
page 48
page 49
page 50
page 51
page 52
page 53
page 54
page 55
page 56
page 57
page 58
page 59
page 60
page 61
page 62
page 63
page 64
page 65
page 66
page 67
page 68
page 69
page 70
page 71
page 72
page 73
page 74
page 75
page 76
page 77
page 78
page 79
page 80
page 81
page 82
page 83
page 84
page 85
page 86
page 87
page 88
page 89
page 90
page 91
page 92
page 93
page 94
page 95
page 96
page 97
page 98
page 99
page 100
page 101 page 102
page 103
page 104
page 105
page 106
page 107
page 108
page 109
page 110
page 111
page 112
page 113
page 114
page 115
page 116
page 117
page 118
page 119
page 120
page 121
page 122
page 123
page 124
page 125
page 126
page 127
page 128
page 129
page 130
page 131
page 132
page 133
page 134
page 135
page 136
page 137
page 138
page 139
page 140
page 141
page 142
page 143
page 144
page 145
page 146
page 147
page 148
page 149
page 150
page 151
page 152
page 153
page 154
page 155
page 156
page 157
page 158
page 159
page 160
page 161
page 162
page 163
page 164
page 165
page 166
page 167
page 168
page 169
page 170
page 171
page 172
page 173
page 174
page 175
page 176
page 177
page 178
page 179
page 180
page 181
page 182
page 183
page 184
page 185
< prev - next > Energy Hydro power civil_works_guidelines_for_micro_hydro (Printable PDF)
CIVIL WORKS GUIDELINES FOR MICRO-HYDROPOWER IN NEPAL
99
piers, and the savings made on the piers may equal or even
exceed the cost of excava-tion and backfill. Since this is a
site-specific case, a cost calculation should be done if buried
mild steel pipe is being considered. Both exposed and buried
penstock pipes require anchor blocks at significant bends.
However, for relatively low head and flow, as well as small
bend angles, the 1 m depth of well compacted soil cover on
buried pipe may be adequate (see Chapter 7, Anchor blocks
and support piers). The nature of the terrain and the soil
depth may also govern whether to bury or expose the penstock
pipe. Buried penstock is not practicable on routes steeper than
30° because the backfill will be unstable. Where top soil is
thin or rock is exposed, the costs involved in excavating the
rock may make burial of the pipe impossible.
6.10 Expansion joints
Penstock pipes are subjected to temperature variations due to
changes in the ambient temperature. When the ambient
temperature is high the pipes will expand and when it drops,
the pipes will contract. Such thermal expansion causes stresses
in the pipes if they are not free to expand.
An above ground penstock is subjected to greater temperature
variations resulting in higher thermal expansion. The thermal
expansion or contraction is highest when the penstock is
empty, such as during installation or repair work. The
temperature variation is relatively low when the pipe is full
since the flow of water with fairly constant temperature
prevents the pipe from rapidly heating up. As long as pipes
are free to move at one end, thermal expansion does not
cause additional stresses. However, a penstock pipe section
between two anchor blocks is kept fixed at both ends. In such
a case thermal expansion could cause additional stresses and
the pipe can even buckle. Therefore, provision must be made
for the penstock pipe to expand and contract, by installing an
expansion joint in a penstock pipe section between two anchor
blocks. The most common type of expansion joint used in
Nepal is of sliding type. This is shown in Figure 6.6 and
Photograph 6.13. Such an expansion joint is placed between
two consecutive pipe lengths and bolted to them. The stay
TABLE 6.3 Comparison between site welding and flange connection
PIPE JOINING METHOD ADVANTAGE
DISADVANTAGE
GENERAL RECOMMENDATIONS AND
COMMENTS
Site welding
Flange connection
Easy to fabricate at
workshop since
flanges do not
have to be welded
at pipe ends.
Higher degree of precision
work required at site to
weld the pipe ends.
Improper welds can cause
leaks and pipe can burst at
high heads.
A properly welded
pipe will not leak
and requires less
maintenance.
Need to transport a
welding machine and a
generator at site. Also
requires supply of petrol/
diesel to site.
Difficult logistics if the site is more than a
day’s walk from the road head.
Generally not economic for small
schemes and/or short penstock lengths.
Select this option only if the site staff are
experienced, site is less than a day’s
walk from the roadhead and penstock
length is more than 50 m.
Easy to install at Fabrication cost is high
site. Site installa- since flanges need to be
tion work involves welded at ends. Also there
placing a gasket is some wastage since the
between the
flange is prepared by
flanges and bolting removing the central disc
them.
of a diameter equal to the
external pipe diameter.
The pipe alignment and
the bends can not be
adjusted at site.
Can leak if the bolts are
not well tightened or if
gaskets are of poor quality.
Flange connection is appropriate for
schemes that are located more than a
day’s walk from the roadhead and/or
have a relatively short penstock length.
Minimum flange thickness should be at
least twice the penstock wall thickness or
8 mm whichever is larger.
A minimum bolt diameter of 12 mm is
recommended.
A minimum gasket thickness of 5 mm is
recommended.
Should be above ground.
Higher risk of vandalism
since the bolts can be
removed.